Home > SEP
Clearance Requirements > Resource Extractive Activities
Republic of the Philippines PALAWAN COUNCIL FOR SUSTAINABLE DEVELOPMENT (R.A. 7611) Puerto Princesa City, Palawan
LIST OF REQUIREMENTS FOR EVALUATION OF SEP CLEARANCE APPLICATIONS
RESOURCE EXTRACTIVE ACTIVITIES
1. Major Mining and Quarrying Activities
a. Mineral Ore processing
EIS: >=70,000 MT annual processing capacity (inputs)
IEE: < 70,000 MT annual processing capacity per
day extraction rate
b. Cement, other cement
products, clinker, limestone and other non-metallic minerals
processing plant
EIS: >=75,000 MT per annum or quarry area >=20
hectares
IEE: < 75,000 MT per annum and quarry area < 20
hectares
c. Off-shore mining (including
extraction of deuterium, oil and gas)
EIS: Regardless of capacity or area 2. Additional requirements to be attached to the EIS:
- Geo-hazard map of the applied area
- Location map/project site plotted on the Topo map with 1:50,000 scale
- Site development plan/map noting adjacent water bodies (scale : 1: 10,000 scale)
- Two-year Exploration Work Program
- Proposed Commercial Production Work Program/Construction and Development Work Program, whichever is applicable
3. Status of Land/Land Claim
- Certification from CENRO/PENRO
- Land Title/Tax Declaration/Stewardship Contract
- For conflict areas: waiver from other claimants
4. Endorsement from the following LGU with
resolution including a copy of documentation
of the consultation process
- Sangguniang Pambarangay
- Sangguniang Bayan/Lungsod
- Sangguniang Panlalawigan
- Indigenous tribal communities in case the area falls within a certified ancestral land/domain
5. Zoning Clearance from the Municipal/City Zoning Office
In case of renewal or expansion, environmental
accounting of previous operation.
|