Home > SEP Clearance Requirements > Agricultural Projects
Republic of the Philippines PALAWAN COUNCIL FOR SUSTAINABLE DEVELOPMENT (R.A. 7611) Puerto Princesa City, Palawan
LIST OF REQUIREMENTS FOR EVALUATION OF SEP CLEARANCE APPLICATIONS
AGRICULTURAL PROJECTS
1. a. Livestock/Poultry projects
EIS: >= 100,000 heads poultry/birds or >=
1,000 heads pigs/goats
IEE: >= 10,000 heads but <100,000 heads
poultry/birds or
>=100 heads but,
1,000 heads pigs/goats
Certificate of Non-Coverage (CNC): <10,000
heads poultry/birds of <100 heads pigs or
goats
b. Agricultural
Plantation
EIS:>= 1,000 hectares
IEE: = 100 hectares but < 1,000 hectares
Certificate of Non-Coverage
(CNC): < 100 hectares
c. Agricultural Processing
facilities
EIS: =>50,000 MT annual production
capacity
IEE: => 5,000 MT but < 50,000
Certificate of Non-Coverage (CNC):
< 5,000 MT annual production capacity
2. Additional Requirements to be attached to the EIS/IEE
- Location map/Project site plotted on the Topo Map with 1:50,000
scale
- Site Development Plan/Map noting water bodies (scale 1:10,000)
- Waste Disposal Plan
3. Social Acceptability Documents such as endorsements from
- Sangguniang Bayan
- Sangguniang Pambarangay
- Sangguniang Panlalawigan
4. Zoning Clearance from the Municipality/City
Zoning Officer
5. Proof of Status of Land and Land Ownership/Land Claim
|