Home > SEP
Clearance Requirements >Dikes for/and Fishpond Development Projects
Republic of the Philippines PALAWAN COUNCIL FOR SUSTAINABLE DEVELOPMENT (R.A. 7611) Puerto Princesa City, Palawan
LIST OF REQUIREMENTS FOR EVALUATION OF SEP CLEARANCE APPLICATIONS
Dikes for/and Fishpond Development Projects
1. a. Fishery/Aquaculture Projects in water bodies
Environmental Impact Statement (EIS): >=100 hectares
Initial Environmental Examination (IEE): >= 1 hectare but <100 hectares
Certificate of Non-Coverage (CNC): < 1 hectare
Additional requirements to be attached to the IEE:
- Location map/project site plotted on the Topographic map with 1:50,000 scale
- Site development plan/map noting adjacent water bodies (scale: 1: 10:000)
- Project site/perimeter map as verified by the CENRO
- Feasibility Studies (if applicable)
2. Status of Land/Land Claim
- Certification/evaluation from CENRO?PENRO
- Land Title/Tax Declaration/Stewardship Contract
- Concession Agreement between the LGU and the Proponent
3. Endorsement from the concerned LGUs with attached resolution including a copy of the documentation of the consultation process undertaken
- Sangguniang Pambarangay (All barangays covered by the project)
- Sangguniang Bayan
- Sangguniang Panlalawigan
- Free and Prior Consent from Indigenous tribal communities in case the area falls within a certified ancestral land/domain
4. Endorsement/Certification from DA-BFAR
5. Resource Management Plan/CRMDP for Fishery Projects
- Proposed Development Management Plan and Annual Operation Plan
- Inventory (100%) of Mangrove Coastal Forest Resources
6. Zoning Clearance from the Municipal/City Zoning Officer
|